Linwood Sewer Renewals - Package 3 (Hay Street)

What

The renewal of the sewer main and laterals in Hay Street.

Why

The existing sewers are reaching the end of their economic life and need to be renewed.

Where

Hay Street, between Linwood Avenue and Butterfield Avenue.

When

Work will start Monday 24 June 2019 for approximately three (3) months.

Contact

The contractor is Downer. Phone 0800 026 420 between7.00am and 6.00pm. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • Traffic management will be installed to keep both the workers and road users safe. 
  • Please be aware that a reduced speed limit will be in place going through the site.
  • There may be times when vehicle access to your property may be restricted.  This will be temporary and our contractor will door knock beforehand so you can move your vehicle if necessary.
  • Hay Street will be relined with a plastic liner as the existing sewer is deep and in poor ground.  The laterals will be renewed along with the main in all streets.

Please phone Downer Contract Manager should you have any questions or concerns.  Phone 0800 026 420.