Westburn Reserve - play space renewal

What

We are renewing the play space in Westburn Reserve. This includes new play equipment and safety surfacing as well as a new section of path and some park furniture.

Why

The play equipment in Westburn Reserve has reached the end of its life and is no longer fit for purpose.
New amenities will be constructed, which will provide a safe and improved play experience.

Where

Westburn Reserve, Burnside.

When

Mid-September 2025 to November 2025. Monday to Friday, 7am to 6pm (weather/site condition dependant).

Contact

The contractor is Curle Contracting Ltd. Contact Jack Curle, phone 021 078 9923, Monday to Friday, 8am to 5pm.

Details

Work to improve the play space at Westburn Reserve is about to get underway.  The work includes:

 

  • Temporary fencing of work site.
  • Site clearance and removal of old play equipment.
  • Installation of new safety surface.
  • Renewal of play equipment to ensure a safe play environment.

 

Temporary fencing will be installed around the work site for the duration of the project. Access to the wider park will remain available.

We anticipate there will be an increase in noise and activity during the construction process. We will be making every effort to minimise the impact of this work as much as possible.

We expect to reopen the play space by November 2025.

 