Owles Terrace - stopbank repair

What

Avon River (Bexley) Stopbank Repairs

Why

To repair minor erosion on the stopbank surface.

Where

Owles Terrace, near the Pages Road bridge. New Brighton.

When

22 September 2025 to 4 October 2025. Monday to Friday, 7am to 5pm (weather/site condition dependent).

Contact

The contractor is City Care. Phone Nathan Woolford on 027 801 7975, Monday to Friday, 7am to 5pm.

Details

We are undertaking maintenance work on the stopbank on Owles Terrace due to minor erosion noted in a recent audit.  There is no risk to the stability of the stopbank.

 

These works will include scraping off loose material and replacing with compacted fill, with the finished surface being topsoil and grass.

Traffic Impacts (see site plan overleaf)

  •          One way only for traffic heading east along Owles Terrace
  •          Detour in place for traffic heading west along Collingwood Street

 

Additional Information

  •          Walking access along the stopbank will be closed for the duration of the work
  • Enviromental controls will be in place to prevent surface run-off to the road or river