What |
We’re relining sections of the brick barrel stormwater drain under Ferry Road. |
---|---|
Why |
Sections of the brick barrel stormwater drain running beneath Ferry Road are damaged and need to be repaired. |
Where |
Sections of Ferry Road near Osborne Street, Smith Street, and Hart Street, Woolston. |
When |
21 July 2025 to late September 2025. For Sections 1 and 2 work will take place from Monday to Friday, 7am to 6pm (weather/site condition dependent). |
Contact |
The contractor is Seipp Construction. Phone 03 660 0315, Monday to Friday, 7am to 6pm. |
This is the final stage of a project to renew damaged sections of the brick barrel stormwater drain. The damage threatens the structural integrity of the drain and needs to be repaired.
The work will be staged and completed in three sections (shown on map).
Traffic impacts
Traffic management will be in place to enable the work to be carried out safely.
Project area map
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch