Nor’West Arc project – Stage 1 phase 3 starting, in addition to ongoing phase 2 works

What

We’re starting the next phase of works to upgrade wastewater pipes and other underground services, extend the Nor’West Arc Cycleway, and complete a street renewal. See below for more detail on the work scope and traffic impacts.

Why

To upgrade old wastewater and water supply infrastructure; to make the roads safer and more accessible for cyclists and pedestrians; and to reconstruct the road and footpaths, which are in need of renewal.

Where

Aorangi Road, between Wairakei Road and Brookside Terrace, Bryndwr.

When

26 May to end of July 2025. Monday to Saturday, 7am to 6pm (weather/site condition dependent).

Contact

The contractor is Isaac Construction. Phone Isaac Construction on 027 323 0056 or email MCRnorwestarc@isaac.co.nz Please advise Isaac Construction if you have any specific property access requirements e.g. medical visits, large deliveries, home help and any planned works.

Details

Project overview: This entire project will be completed in three stages and involves upgrading the wastewater pipes, installing a new stormwater network and making water supply upgrades; completing the northern-most section of the Nor’West Arc Cycleway (Ilam Road / Aorangi Road intersection to Matsons Avenue / Harewood Road intersection); and renewing Aorangi Road. For each stage/location, the package of work will be delivered together, with all work completed by mid-2026.

The Stage 1, phase 3 programme is located on Aorangi Road (south), between Wairakei Road and Brookside Terrace.

Phase 3 work scope:

 Major wastewater and underground service upgrades along Aorangi Road.

 Preparations for future kerb and channel, road and footpath renewals.

 Cycleway construction.  

 

At times, night work may be required. Prior to this happening, those who may be impacted by the work will receive further notification from the contractor.

 

This work overlaps some Stage 1, phase 2 works on Wairakei Road and Aorangi Road (north), which are still ongoing.

Phase 2 update

 

The transition back to two-way traffic on Wairakei Road is now expected to take place by the end of July. This delay is due to a combination of wet weather, challenging ground conditions, and higher than usual groundwater levels. These factors have required additional care during excavation and construction, particularly around critical work like manhole connections and trench backfilling. We’re sorry for any inconvenience caused by this delay.

 

Traffic Impacts

 

  • The citybound one-way system on Wairakei Road will remain in place until end of July. A detour is in place for the airport-bound route.

 

  • The existing closure at the southwest approach to the intersection of Wairakei Road and Aorangi Road will extend to just north of Colwyn Street until end of July, with access maintained for residents and businesses only. Access to Aorangi Road (south) will be maintained from the southwest end of the road and through side streets, such as Clyde Road and Brookside Terrace.

 

  • Aorangi Road (north) will remain one-way system, with entry from Condell Avenue only and left-turn exit only onto Wairakei Road, until end of August. Detours are in place.
    Note: As this notice focuses on impacts in place between 26 May and end of July, this one-way system will be recaptured in the next start works notice, which will focus on the period starting end of July / beginning of August and ending in late October, when all Stage 1 works are expected to be complete.

 

Information for residents and businesses:

  • There will be no on-street parking in the work area
  • Businesses will remain open as usual
  • Please follow pedestrian and cycle signs when visiting businesses
  • Signposted customer parking will be available on both Aorangi and Wairakei Roads.

Keep in touch:

  • Visit ccc.govt.nz/norwestarc/ for general project information. For any enquiries, or to request updates, please call or text Isaac Construction on 0273230056 or email MCRnorwestarc@isaac.co.nz
  • Isaac Construction hold a resident drop-in session on the first Tuesday of every month at 5pm at Elmswood Retirement Village, 56 Colwyn Street – feel free to come along with any questions or feedback.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Takiuru ki ā mātou ratonga
Log in to our services