McBratneys Road - Odour Treatment

What

Installing a new Odour Dome outside 19 McBratneys Road and corrosion protection coating to the sewer manholes around this area. With a planned road closure for Banks Avenue during the day for the above manhole work.

Why

To remove the odour from the sewer manholes in this area.

Where

19 McBratneys Road and surrounding area, Dallington.

When

2 May 2025 to 6 June 2025. Monday to Friday, 8am to 5pm (weather/site condition dependent).

Contact

The contractor is Seipp Construction. Phone 03 660 0315, Monday to Friday, 8am to 5pm.

Details

Christchurch City Council has contracted Seipp Construction to undertake the construction of an Odour Dome that connects to the existing network outside 19 McBratneys Road.

 

There will be a road closure required to undertake the corrosion protection coating to manholes and blocking vents on the sewer manholes work on Banks Avenue, which is planned for the weeks of 12 May 2025 to 23 May 2025, during work hours only.  We will also be blocking the existing vents to the sewer manholes in your area.

Thank you for your patience as we upgrade the sewer network in your area.