We’re building the next stage of the Nor'West Arc cycleway to make it safer and easier for people to cycle in Bryndwr. We're also upgrading wastewater pipes in the area at the same time.
Thanks for your patience while we complete the upgrades.
In January 2025, work began on constructing the northernmost section of Te Ara O-Rakipaoa Nor'West Arc cycleway. We're also completing wastewater pipe renewals in the area, installing a new stormwater network, making water supply upgrades, and completing a street renewal on Aorangi Road.
These projects have been programmed together to ensure a coordinated approach to work in the area. The work is being completed in three stages, with the full project scope expected to be complete by mid-2026.
View the traffic impacts drop-down tab below for information on the current phase of work and associated impacts.
Businesses are open throughout the works, and customers are encouraged to continue visiting as usual.
Parking will continue to be signposted, although the locations may adapt as work progresses. Please follow the signs. Footpath detours are also in place to ensure safe pedestrian access to businesses and through the work area.
Work to construct the next section of the Nor’West Arc cycleway has been timed with significant Three Waters upgrades, to ensure a coordinated approach to work in the area. The construction programme is scheduled to begin on 13 January and is expected to wrap up around mid-2026. The work will be delivered in three stages. Example of a two-way cycleway Throughout the project, there will be temporary traffic management in place to keep road users and contractors safe. Please take care to follow signage and reduce speeds when travelling through the work site. Wairakei Road citybound one-way system, in place until the end of July 2025: Aorangi Road (north) one-way system, in place until the end of August 2025: Aorangi Road (south), until 30 June 2025: Aorangi Road (south), from 30 June to the end of July 2025: Workers will be on-site Monday to Saturday, 7am to 6pm, but the lane and road closures will be in place at all times. At the end of July, two-way traffic will be reinstated on Wairakei Road. Then, for the final months of stage one work, the following impacts will be in place: The project is being completed in three stages, as shown on the map below. Stages may overlap, whereby some work continues in an area while work at the next area starts. The entire project is expected to be completed in mid-2026. Each stage will also have different phases of work, marked by distinct changes in things such as the work area and the traffic management in place. We will sent out Start Work notices for each phase of work, which will provide the specific details of the work and its impacts. Stage 1, phase 2 work is underway and centres around the Aorangi Road/Wairakei Road intersection, as well as the northern section of Aorangi Road. We'll keep up-to-date information on the impacts of the current phase in the tab below.
Key works for all three stages of the project
Current impacts
Impacts from the end of July to October 2025
Phasing of work
Subscribers of our general project updates(external link) will be notified by email when the project moves into a new stage/phase and there are changes to traffic management and the work area layout. We may also let you know about key milestones we've achieved.
If you would like to receive more information about the project's progress from our contractor, Isaac Construction, you can sign up(external link) for their email updates, which will be sent more regularly. Additionally, residents or businesses located within, or close to, the work area can sign up for the contractor's site-specific text alerts and email updates on the work(external link).
Te Ara O-Rakipaoa Nor'West Arc cycleway connects cyclists from Cashmere to Bryndwr, via Spreydon, Middleton, Riccarton and Ilam. The route begins at Princess Margaret Hospital in Cashmere and is currently open as far as Jellie Park Recreation and Sport Centre on Ilam Road.
The cycleway provides a safer route for cyclists to get to school, university, work, pools and gym, parks, and local shops. Making it safer for people to bike helps reduce congestion, lowers emissions and makes it easier for cyclists to get around.
North of the intersection of Aorangi and Ilam roads, we're extending the cycleway along the full length of Aorangi Road, then onto Condell Avenue and up Matsons Avenue to Harewood Road. Find more information in the sections above about how this work will be staged.
When this section has been constructed, the route will be complete, except for a short section at approximately the midpoint of the route, along Annex Road.
We will come back to the Annex Road section, between Birmingham Road and Blenheim Road, at a later date. We'll need to work alongside KiwiRail to improve safety and access at the level crossing that intersects the route.