We’ve built a new link road, opening soon, to provide a safer and more direct route for traffic travelling along Halswell Junction Road.
We’re doing the final works necessary for opening the new road link on Halswell Junction Road, due to open to traffic on Thursday 22 May (end of the day).
Both night and day work will be undertaken by KiwiRail as they work on the railway between Friday 16 May and Thursday 22 May 2025. To enable KiwiRail to work safely on the railway, level crossing closures will be in place as follows:
Detours are in place. Please allow more time when travelling through the area, especially during morning peak traffic on Monday 19 to Thursday 22 May. Find more information on this webpage.
The new road link is located just north of Main South Road, extending Halswell Junction Road in a northwest direction from Foremans Road to Waterloo Road over a new level crossing to a new signalised intersection.
Road and railway works, as well as extensive safety testing by KiwiRail, are required before the road can open, approximately at the end of the day on Thursday 22 May 2025.
KiwiRail will be working on the new and existing level crossings from 16 to 22 May, and on two adjacent level crossings from 18 to 22 May. Road works will also be undertaken during this time to prepare for the opening. To enable KiwiRail's works to be completed safely, road closures at the level crossings are required – see below for more details.
The new road link, level crossing and signalised intersection will provide safer and easier access onto Waterloo Road for all road users, including heavy haulage vehicles, buses, cars, cyclists and pedestrians.
The existing section of Halswell Junction Road, renamed Panther Place in April 2025, will be made into a cul-de-sac once the new road link opens. The map above highlights the key changes to the road layout. More information is provided in the tab below on the project features and benefits.
Level crossing closures in May 2025
The existing level crossing on Halswell Junction Road closed permanently from 6pm on Friday 16 May. The new road is expected to open by the end of the day on Thursday 22 May.
The rail work required to commission the new level crossing and close the existing level crossing is complex and involves a signalling system changeover and a series of safety tests.
Although the new level crossing is situated on Halswell Junction Road, the signalling infrastructure runs approximately 5km up and down the railway from this point, so the other nearby level crossings, on Pound Road and Parker Street / Gilberthorpes Road, are affected.
Work along the railway will be done mostly at night between Friday 16 May and Thursday 22 May. Road closures at the level crossings, and detours (see map below), will be in place at the following times:
- Pound Road at the level crossing: from 18 May to 21 May, this level crossing will be closed nightly (four nights) between 7pm and 9am. From 9am to 7pm, this level crossing will be open to traffic.
- New road link for Halswell Junction Road: this road and level crossing will remain closed (as they are currently) until commissioning of the new level crossing is complete. Providing all tests are passed, the new road link will open at the end of the day, Thursday 22 May.
- Existing Halswell Junction Road (now Panther Place) at the level crossing: on 16 May 2025, this level crossing closed permanently and the decommissioning process is now underway. There will no longer be access for vehicles or pedestrians to cross the railway line at this location.
- Parker Street / Gilberthorpes Road at the level crossing: from 18 May to 21 May, this level crossing will be closed nightly (four nights) between 7pm and 9am. From 9am to 7pm, this level crossing will be open to traffic.
We know these road closures will be disruptive, and we apologise for any inconvenience. Please allow extra travel time and follow the signposted detours. Detour information, including a map, is provided below.
Thank you for your patience as we carry out these essential works to prepare for the opening of the new road link.
From 6pm on 16 May, the existing railway level crossing at the intersection of Halswell Junction Road (now Panther Place) and Waterloo Road will be permanently closed and decommissioned. The intersection will also permanently close, with no vehicle or pedestrian access over the railway at this point.
Once the new road link opens, work will begin on making the old road link into a cul-de-sac, south of the railway line. The road was renamed Panther Place in April 2025.
The new street name for the cul-de-sac was consulted on with properties in this section of the street, and on 14 December 2023, the Waipuna Halswell-Hornby-Riccarton Community Board approved the name Panther Place.
Designed to improve efficiency and safety, this project delivers several important benefits, including:
To bring the project to completion, some final works will be carried out in 2025. The impact of these works will vary, as follows:
With road closures required on three busy roads in Islington/Hornby – Pound Road, Halswell Junction Road and Parker Street / Gilberthorpes Road – this programme of work is expected to bring disruption to the area.
Signposted detours will be in place during the closure periods. See above text box for closure locations and timings, and click the tab below for a detour map.
Key works we're doing:
Once the commissioning process is complete, the new road link will open for use immediately.
This will be communicated to the public through a variety of channels, and additional signage will be on the road to direct traffic onto the new road.
The remaining work will focus on Panther Place and Waterloo Road, with more localised impacts.
Key works we'll be doing:
More information about impacts for traffic, residents and businesses will be provided closer to the time in a work notice.
We have completed the following key works:
Additional features:
Thanks for your patience as we complete the remainder of the work for this project.
The detour map below reflects which roads will be used for detours when all three level crossings are closed – Pound Road, Halswell Junction Road and Parker Street/Gilberthorpes Road.
This will be nightly, from 7pm to 9am the next day, on the following four nights:
The detour map shows which roads are open during these times to all vehicles, with some additional roads available to light vehicles (i.e. no trucks).
Outside of the above times, during the 16 to 22 May programme of work, starting 6pm on 16 May – only the Halswell Junction Road level crossing will be closed. This means traffic can use Pound Road and Parker Street/Gilberthorpes Road in addition to any roads marked on the detour map during the following times:
Halswell Junction Road is then expected to open on Thursday 22 May at the end of the day.
We know these road closures will be disruptive, and we apologise for any inconvenience. Please allow extra travel time and follow the signposted detours.
This project was consulted on between 1 September and 25 September 2017.
The community provided feedback on the proposed options for the project, which included:
Option 1 – New link
Option 2 – Upgrade of the existing road link
Option 3 – Do nothing
Find out more about the consultation.(external link)
On 30 January 2018, the Waipuna Halswell-Hornby-Riccarton Community Board met to discuss the proposal. Out of the three options, the new link was the preferred choice. The updated plans were also discussed at the Community Board meeting.
On 1 March 2018, Council approved the updated plans for the Halswell Junction Road Extension.
Our contractor is Fulton Hogan. You can contact them on 0800 ROAD FH (0800 7623 34) 24 hours / 7 days.