Get the latest updates on the wastewater treatment plant.

Sign up to the Christchurch Wastewater Treatment Plant newsletter

Contractor appointed for Activated Sludge Reactor 

The main construction contract for the Christchurch Wastewater Treatment Plant's Activated Sludge Reactor has now been awarded to HEB Construction, marking a major milestone for the upgrade.

We’re working closely with the contractor to get the site established as soon as possible, with construction expected to start early in the new year. 

This work follows the demolition of the fire-damaged trickling filters earlier this year, clearing the way for the new reactor. Construction is expected to take about three years, with commissioning targeted for 2028.

Once the new facility is operational, it will provide a long-term solution to the odour issues experienced since the fire, while also reducing greenhouse gas emissions and increasing capacity to support our growing population.

We know the fire and its aftermath have had a significant impact on the community, and we appreciate how challenging this period has been. While it has taken time to get to this point, we can now move from planning into delivery, and that’s great news for the plant and the wider community.

Clarifier repair work planned 

Alongside this work, we’re continuing preparation work for a project focused on repairing the clarifiers, which play a vital role in separating solids from treated wastewater before it flows to the oxidation ponds.

The cutoff wall trial continues. This will allow us to isolate the clarifier tanks - a key preparatory step for critical repair works scheduled to begin in March. If the trial is successful, the walls will be installed towards the end of this year, streamlining the upcoming repairs and reducing the impact on normal operations.  

Community meeting planned for December 

A community meeting is planned for December, where Council staff will be on hand to answer questions about the Activated Sludge Reactor project, the upcoming clarifier work, and ongoing operations at the treatment plant. This will be an opportunity for residents to learn more about the upgrades and share feedback.

Once a date is confirmed we'll share the information through a range of channels, including this newsletter, our website and a letterbox drop to surrounding residents. 

Midge control measures trialed 

To prepare for the upcoming midge season, the team recently conducted a dredging trial. The test involved towing the midge dredge, which uses chains to disturb the pond’s sludge layer. This disruption helps break the midge lifecycle by displacing or burying larvae.

The trial was timed to ensure conditions were optimal for minimising odour risk. Aerial images captured during the process show the dredge in action, with sludge rising to the surface where it was disturbed. These images also highlight a key concern – some sludge remained on the surface rather than resettling, reinforcing the potential for odour generation.

Odour monitors were in place throughout the trial, and data from the following 24 hours was analysed. Results confirmed that dredging can influence odour levels – an impact likely to be greater when pond health is poor.

Overall, the trial validates the cautious approach we’ve taken in previous summers while confirming that dredging could be a viable option under the right conditions.

Timeline of key events and decisions

November 2021

  • On 1 November 2021, emergency services respond to a fire at the Wastewater Treatment Plant in Bromley. Both of the trickling roof filters collapse. The damage couldn't be assessed properly until the fire was completely out.
  • On 4 November, the Council installed a sprinkler system to remove hot spots and help reduce the smell. We also begin working on an adaptive management plan to figure out the best possible outcome for the discharge of wastewater from the plant.
  • On 26 November, the fire is officially completely extinguished by the fire service. The Council identifies the need to remove the two trickling filters. Both filters store 13,000 cubic metres of material.
  • The Council started using misters and polyaluminium chloride - an odourless powder that dissolves in water - to help suppress the smell. Polydosing also settles more of the suspended solids in the wastewater, improving the water quality as it progresses through the plants.
  • Hydrogen peroxide - a compound that naturally breaks down into water and oxygen – starts to be added to the wastewater before it’s discharged into the oxidation ponds.

December 2021

  • On 6 December, the Council completed a successful trial to remove a section of the fire-damaged media from the plant. This means the Council could begin assessing the stability of the structures.
  • On 17 December, Council staff planned to convert two of the plant’s four clarifier tanks (or secondary contact) into aeration tanks. Installing four aerators in each of the two tanks will help decrease the bad smells and improve the quality of the wastewater being discharged. The Council anticipated that it would be years before the trickling filters could be replaced or rebuilt.

February 2022

  • On 14 February, aeration components begin to arrive to implement the interim plan to minimise odours from the fire-damaged plant.

March 2022

  • On 16 March, eight aerators are installed in two of the plant’s four clarifiers.
  • Soon afterwards, increased odours from the trickling filters are detected after wet weather. It's determined that the acute stench is caused by the material inside the trickling filters rotting and drying out.

April 2022

  • On 6 April, the aerators installed in March are turned on.
  • On 12 April, the Council decided to fast-track the appointment of a contractor to remove the burnt filter material.

May 2022

  • Filter media removal work starts.
  • On 6 May, independent testing to better understand the odours from around the fire-damaged plant detects small amounts of hydrogen sulphide and methyl mercaptan.
  • On 26 May, the Council confirms a community support package for 3,380 of the most affected residents.

June 2022

  • Southern Demolition and Salvage Limited conducted a test run, removing and transporting the burnt trickling filter material on Friday 3 and Saturday 4 June.
  • Work to remove the trickling filter began on 6 June.

July 2022

  • The new activated sludge treatment process becomes fully operational at the plant.
  • This new system pumps wastewater from the converted aeration basins to the clarifiers, which greatly improves the quality of the wastewater.

August 2022

  • Trickling filters are emptied one month ahead of schedule.

September 2022

  • Odours from the oxidation ponds are expected to reduce from September, although it is expected that some odours will remain for most of the month. These will progressively reduce as the pond's health improves.

April 2023

  • A project to increase the biological health of Pond 1 is completed after 16 aerators are installed and turned on, churning more than 300kg of oxygen into the pond every hour.
  • In the long term, these aerators will ensure the entire pond continues to stay healthy and function well.

May 2023

  • The disc aerators on Pond 1 failed and were in the process of getting repaired.

Late 2023

  • Fencing around oxidation ponds was installed to improve safety and reduce rubbish entering ponds. Subsequent minor changes were made to deter birds and improve effectiveness.
  • Insurance negotiations were continuing.
  • In November, a report on the insurance claim for the November 2021 fire was provided to the Council. 
  • In December, aerators on Oxidation Pond 1 restarted to minimise odours.

March 2024

  • A report on the insurance process and odour mitigation efforts was provided to the Council.
  • Odour mitigation plan released. 
  • Odour mitigation work is underway. Various actions taken to improve plant performance and reduce odour. 
  • A new interactive map was created showing odour mitigation work. 

April 2024

  • Ponds switched to winter operation mode. Adjustments made to our operations to reduce odours when the biology changes as weather cools. 

May 2024

  • The Mayor and councillors approved a grant of $130,000 to resource a project with the goal of strengthening and sustaining effective and respectful relationships with Eastern Communities.
  • Completed work to cover inlet chambers to contain odour. 
  • Completed replacement of the bio-bed material in the odour control system. Old material reused as soil conditioner for native planting areas.

October 2024

  • Christchurch City Council and its insurers have agreed on a settlement in relation to the fire-damaged trickling filters at the Christchurch Wastewater Treatment Plant.
  • The Council also approved the replacement of the trickling filters with an activated sludge reactor.
  • This significant milestone allows us to move forward with building a resilient and more environmentally friendly wastewater treatment plant for our growing city.
  • Replacing the trickling filters with an activated sludge reactor will give the Council the opportunity to significantly reduce greenhouse gas emissions. Additionally, activated sludge reactors can deliver better environmental outcomes and have a smaller footprint that can be cost-effectively upsized to accommodate the needs of our growing population.
  • Design work is underway and it’s expected to take up to three years to complete the design and construction of the new activated sludge reactors.

November 2024

  • Demolition of the Christchurch Wastewater Treatment Plant’s fire-damaged trickling filters started.
  • Southern Demolition is doing the work, which is expected to take four to five months to complete. 
  • The demolition is the first stage of physical work to replace the filters with an activated sludge reactor, which will fix long-standing odour issues. 

April 2025

  • Demolition of the trickling filters was completed making way for construction to begin on the the new activated sludge reactor later this year. 

November 2021

  • On 1 November 2021, emergency services respond to a fire at the Wastewater Treatment Plant in Bromley. Both of the trickling roof filters collapse. The damage couldn't be assessed properly until the fire was completely out.
  • On 4 November, the Council installed a sprinkler system to remove hot spots and help reduce the smell. We also begin working on an adaptive management plan to figure out the best possible outcome for the discharge of wastewater from the plant.
  • On 26 November, the fire is officially completely extinguished by the fire service. The Council identifies the need to remove the two trickling filters. Both filters store 13,000 cubic metres of material.
  • The Council started using misters and polyaluminium chloride - an odourless powder that dissolves in water - to help suppress the smell. Polydosing also settles more of the suspended solids in the wastewater, improving the water quality as it progresses through the plants.
  • Hydrogen peroxide - a compound that naturally breaks down into water and oxygen – starts to be added to the wastewater before it’s discharged into the oxidation ponds.

December 2021

  • On 6 December, the Council completed a successful trial to remove a section of the fire-damaged media from the plant. This means the Council could begin assessing the stability of the structures.
  • On 17 December, Council staff planned to convert two of the plant’s four clarifier tanks (or secondary contact) into aeration tanks. Installing four aerators in each of the two tanks will help decrease the bad smells and improve the quality of the wastewater being discharged. The Council anticipated that it would be years before the trickling filters could be replaced or rebuilt.

February 2022

  • On 14 February, aeration components begin to arrive to implement the interim plan to minimise odours from the fire-damaged plant.

March 2022

  • On 16 March, eight aerators are installed in two of the plant’s four clarifiers.
  • Soon afterwards, increased odours from the trickling filters are detected after wet weather. It's determined that the acute stench is caused by the material inside the trickling filters rotting and drying out.

April 2022

  • On 6 April, the aerators installed in March are turned on.
  • On 12 April, the Council decided to fast-track the appointment of a contractor to remove the burnt filter material.

May 2022

  • Filter media removal work starts.
  • On 6 May, independent testing to better understand the odours from around the fire-damaged plant detects small amounts of hydrogen sulphide and methyl mercaptan.
  • On 26 May, the Council confirms a community support package for 3,380 of the most affected residents.

June 2022

  • Southern Demolition and Salvage Limited conducted a test run, removing and transporting the burnt trickling filter material on Friday 3 and Saturday 4 June.
  • Work to remove the trickling filter began on 6 June.

July 2022

  • The new activated sludge treatment process becomes fully operational at the plant.
  • This new system pumps wastewater from the converted aeration basins to the clarifiers, which greatly improves the quality of the wastewater.

August 2022

  • Trickling filters are emptied one month ahead of schedule.

September 2022

  • Odours from the oxidation ponds are expected to reduce from September, although it is expected that some odours will remain for most of the month. These will progressively reduce as the pond's health improves.

April 2023

  • A project to increase the biological health of Pond 1 is completed after 16 aerators are installed and turned on, churning more than 300kg of oxygen into the pond every hour.
  • In the long term, these aerators will ensure the entire pond continues to stay healthy and function well.

May 2023

  • The disc aerators on Pond 1 failed and were in the process of getting repaired.

Late 2023

  • Fencing around oxidation ponds was installed to improve safety and reduce rubbish entering ponds. Subsequent minor changes were made to deter birds and improve effectiveness.
  • Insurance negotiations were continuing.
  • In November, a report on the insurance claim for the November 2021 fire was provided to the Council. 
  • In December, aerators on Oxidation Pond 1 restarted to minimise odours.

March 2024

  • A report on the insurance process and odour mitigation efforts was provided to the Council.
  • Odour mitigation plan released. 
  • Odour mitigation work is underway. Various actions taken to improve plant performance and reduce odour. 
  • A new interactive map was created showing odour mitigation work. 

April 2024

  • Ponds switched to winter operation mode. Adjustments made to our operations to reduce odours when the biology changes as weather cools. 

May 2024

  • The Mayor and councillors approved a grant of $130,000 to resource a project with the goal of strengthening and sustaining effective and respectful relationships with Eastern Communities.
  • Completed work to cover inlet chambers to contain odour. 
  • Completed replacement of the bio-bed material in the odour control system. Old material reused as soil conditioner for native planting areas.

October 2024

  • Christchurch City Council and its insurers have agreed on a settlement in relation to the fire-damaged trickling filters at the Christchurch Wastewater Treatment Plant.
  • The Council also approved the replacement of the trickling filters with an activated sludge reactor.
  • This significant milestone allows us to move forward with building a resilient and more environmentally friendly wastewater treatment plant for our growing city.
  • Replacing the trickling filters with an activated sludge reactor will give the Council the opportunity to significantly reduce greenhouse gas emissions. Additionally, activated sludge reactors can deliver better environmental outcomes and have a smaller footprint that can be cost-effectively upsized to accommodate the needs of our growing population.
  • Design work is underway and it’s expected to take up to three years to complete the design and construction of the new activated sludge reactors.

November 2024

  • Demolition of the Christchurch Wastewater Treatment Plant’s fire-damaged trickling filters started.
  • Southern Demolition is doing the work, which is expected to take four to five months to complete. 
  • The demolition is the first stage of physical work to replace the filters with an activated sludge reactor, which will fix long-standing odour issues. 

April 2025

  • Demolition of the trickling filters was completed making way for construction to begin on the the new activated sludge reactor later this year.