Berry Street - St Albans wastewater renewals

What

We’re replacing wastewater pipes which are part of the St Albans Wastewater Renewal Project.

Why

The existing wastewater pipes have reached the end of their service life and require replacing.

Where

Berry Street.

When

Work will start 8 July 2020 to mid-September 2020.

Contact

The Contractor is Citycare and their representative is Jermaine Thinnasagaren, project manager (027 260 6350). Please advise Jermaine if you have specific property access requirements re: medical visits, home help, large vehicle deliveries, planned works.

Details

There may be times when vehicle access to your property is restricted.  This will be temporary and our contractor will door knock beforehand so you can move your vehicles if necessary.

The work may result in increased dust, noise and vibrations.  We will try to keep any disruption to a minimum and we apologise in advance for any inconvenience.

All work is subject to favourable weather and on-site construction conditions.

 