Lyttelton Harbour Wastewater Project

What

Closing off part of Ferry Road to install a wastewater pipeline connecting the Lyttelton and Christchurch wastewater systems.

Why

To install a wastewater pipeline

Where

From St Johns Street in Woolston to the paddocks, parallel to Tunnel Road

When

8pm Saturday 25 January until 10am Sunday 26 January 2020

Contact

Fulton Hogan on 0800 342 48457 (0800 FHCIVILS) or 027 604 9335 (Mon - Fri, 8am- 6pm) or email

We’re planning night works and need to close part of Ferry Road from St Johns Street to the Ferry Road roundabout so we can install 535 metres of wastewater pipeline.

The Eastbound lane of Ferry Road will remain open, while Westbound traffic will be detoured, with clear traffic management in place.

There will be plans in place to allow you access to your property, although there will be no on street parking on Ferry Road available during this time.

Pedestrian access will be open at all times.

These night works will be completed in a single shift from 8pm Saturday night until 10am Sunday morning, to minimise disruption to residents.

If we need to do extra work outside of these times, we'll let you know.

We’ve scheduled this work for the end of January and expect it to be completed in one 14-hour night shift.

We’ll confirm the exact dates of this work before Christmas.

This work is part of a project to connect Lyttelton Harbour’s wastewater to the main Christchurch system