Scotston Ave - Dudley Creek waterway lining upgrade

What

We are installing new timber lining in Dudley Creek waterway.

Why

Renewal of a section of the waterway lining which is in poor condition.

Where

Adjacent to Scotston Avenue between Mays and Tomes Road in Papanui

When

From 7 March 2022 to late May 2022. Works are restricted to Monday to Friday 7:00 am to 6:00 pm, Saturday 8:00 am to 12:00 pm. (weather/site condition dependent).

Contact

The Contractor is City Care Ltd. Phone Aaron Martin on 027 215 8759, Monday to Friday, 7am to 5:30pm, after hours on 0508 248 922.

Details

  • Renewal of a dilapidated section of the waterway adjacent to Scotston Avenue between Mays and Tomes Road.
  • Some timbers are rotting or missing and some areas with concrete lining has bulged out.
  • New timber lining will be installed and includes some landscape planting, fish shelters and eel habitat alcoves.

Takiuru ki ā mātou ratonga