Hackthorne Rd / Dyers Pass Rd - water supply mains renewal

What

The renewal of Water Supply mains in Hackthorne Rd and Dyers Pass Rd.

Why

To replace and upgrade existing water mains and lateral connections which has reached its end of lifecycle.

Where

104 to 127 Hackthorne Rd., Hackthorne/Dyers Pass Rd. intersection, 97 to 164 Dyers Pass Rd.

When

October 4th to early-August 2022, 7am to 6pm. (weather/site condition dependent).

Contact

The contractor is Tru-Line Civil Ltd. Office number: 03 768 6862. Site contact number: phone Shane O’Kelly 020 4080 4936.
Alternatively contact Christchurch City Council (03) 941 8999.

Details

  • Traffic management will be installed to keep both road users and workers safe.
  • Please be aware, reduced speed limits will be in place during construction works.
  • On road parking will be limited during the works.
  • During construction works, both the water supply mains and lateral connections to the property boundary will be accessed including work across berms and footpaths.
  • The new water main will be tested and you will be informed via another letter drop prior to any water shut down.
  • Pedestrian access will be maintained. Vehicle access to properties may be affected through the day but will be reinstated in the evening using steel plates if required.
  • Night works will occur during the project construction.
  • Please advise us if you have specific access requirements: eg.- medical visits, home help,  large vehicle deliveries and any planned works.

·         

 