Settlers Hill - Wastewater Renewal

Update

What

Renew wastewater pipes.

Why

To increase resilience of the wastewater reticulation in this section.

Where

The lower end of Settlers Hill from Rue Balguerie to the other side of the bridge.

When

Work will start on 19 October 2020 and is expected to be completed by 13 November 2020.

Contact

The contractor is City Care. Phone 027 260 6350.

Details:

Traffic management will be in place. A road closure will be in place for the general public. The contractor will maintain restricted access for local residents and emergency services and will liaise with residents prior to works commencing.

 