Christchurch Waste Treatment Plant - security fencing

What

We are constructing security fencing around the waste treatment plant oxidation ponds.

Why

To provide improved oxidation pond security and access points for authorised personnel.

Where

Around the perimeter of the Bromley treatment plant oxidation ponds.

When

9 January 2023 to late May 2023. Monday to Friday, 7am to 6pm (weather/site condition dependent).

Contact

The contractor is Seipp Construction Limited. Phone Shaun Moore on 027 809 2390, Monday to Friday, 8am to 5pm. Phone Sean Mcwhinney on 027 239 1872, Saturday and Sunday, 8am to 5pm.


Details 

  • Construction of over 8kms of 1.8-metre-high netting fencing around the treatment ponds perimeter
  • Security gating installed for operational entry/egress
  • There will be no traffic management required as all works will be undertaken within the treatment plant boundary
  • The works undertaken will abide by the Department of Conservation permit for lizard management and follow breeding bird management requirements.