What |
Underpinning and filling of voids in the seawall. |
---|---|
Why |
To reinstate support to the base of the seawall and prevent further scouring behind the wall. |
Where |
Near the Pigeon Bay end of Holmes Bay Road. |
When |
Work will start in the week of 12 April 2021 and is expected to be completed by early May 2021 (weather, tides and site dependent). Work will be undertaken between Monday to Friday, 7.30am to 6pm. |
Contact |
The contractor is City Care Ltd. Phone 03 941 7200 between Monday to Friday, 8am to 5pm. |
The road will remain open to single lane traffic during construction, however there may be slight delays at times while concrete trucks are on site.
The works involve:
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.
Other projects
Learn more about our work.
ccc.govt.nz/works
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch