Hagley Park - Armagh Street to carpark footpath renewal

What

We are renewing the footpath in Hagley Park from the Armagh Street Bridge to the Botanic Gardens carpark.

Why

We are renewing this section of footpath by upgrading to an asphaltic concrete surface for improved pedestrian access to the Botanical Gardens.

Where

Hagley Park.

When

Work will start in February 2021 and is expected to be completed by March 2021 (weather dependent).

Contact

The main contractor is Pidgeon Contracting Ltd. Phone 03 323 4231 between Monday and Friday, 8am to 5pm.

Details

Sections of this existing footpath will be closed and temporary footpath access will be in place throughout the duration of this project.

Temporary site fencing and signs will be in place, as well as on site spotters to safely assist pedestrians and motorists around the construction zone during this time.

The Armagh Street carpark will remain open at all times during this renewal process with just one parking bay to be closed off for construction related activities and site access.   

There will be heavy machinery operating with construction plant and vehicle movements taking place during the day.

There may be increased noise and dust during these works.

Thank you for your understanding and cooperation.