Frees Creek Timber Lined Drain Renewal

What

Timber lined drain renewal works

Why

To renew the existing timber lined section of the drain, which has reached the end of its useful life.

Where

Frees Creek, located between 62 and 66 Sherborne Street, Saint Albans, Christchurch 8014.

When

Work will start Monday 4th November 2019 to Friday 6th December 2019. Work is expected to take only 2 weeks within this period, the Contractor will advise on the exact start and finish date.

Contact

The contractor is City Care Ltd. Please phone Brent Cations on 0272152224 between 9:00am – 5:00pm Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

 

 

The timber-lined section of Frees Creek, approx. 22.5m long section, located between 62 and 66 Sherborne Street has reached the end of its useful life. As a result, Christchurch City Council appointed a Contractor (City Care Ltd) to renew the timber-lined drain.

The Contractor will perform the renewal works from 62 and 66 Sherborne St properties as agreed with the property owners. During the works, there may be potential access impact to the garages and driveways due to the location of the existing drain. The Contractor will advise the residents on any such restrictions ahead of the works.