Woolston 2 - wastewater mains renewal

What

Renewal of wastewater mains in Woolston.

Why

To replace and upgrade existing wastewater mains and lateral connections that have reached the end of their life.

Where

Edmonds St; Randolph St; Marcroft St; Manning Pl; Wildberry St; Okeover St; Hopkins St.

When

20 September 2021 to late-May 2022. Monday to Friday, 7am to 5pm and Saturdays 7am-2pm where applicable (weather/site condition dependent).

Contact

The contractor is John Fillmore Contracting. Please phone Eden Sloss, Stakeholder Liaison on 021 420 745 during work hours, unless it’s urgent, anytime is fine.

Details

  • The works will be staged, with the first stage happening at Marcroft street.
  • The second stage will happen on Hopkins Street
  • Traffic will be managed to keep road users and workers safe.
  • Access to properties will be maintained using steel plates, where needed.
  • On-road parking will be limited during the works.
  • Wastewater mains and lateral connections to property boundaries will need to be accessed, including work across berms and footpaths.
  • Please advise the contractor if you have any specific access requirements – e.g. medical visits, home help, large vehicle deliveries, or any planned works to your property.
  • You will receive further updates about when work will begin on your street, and this will include information about any planned night works or wastewater shutdowns, if needed.

Takiuru ki ā mātou ratonga