1. That the stormwater cost sharing contribution for the Halswell Junction Road cost Sharing Area be calculated using the following formula: [Cost Sharing Contribution (City Plan) X CPI Adjustment X Site Factor] + GST.
2. That the wording of the resolution be amended to read:
(a) "a revised sewer contribution rate of $4,437.29/ha (June 1994) subject to escalation, be adopted and applied where the land is subdivided or developed by a land use within the sanitary sewer catchment appurtenant to the Halswell Junction Road area"
(b) "a revised stormwater contribution rate of $17,717.65/ha, (June 1994) subject to escalation, be adopted and applied where the land is subdivided or developed by a land use within the stormwater catchment appurtenant to the Halswell Junction Road area"